Clients

ABL NORWAY

Development Type

Tyra Re-Development

Scope of Work

Weighting Of TEG Deck

The Tyra Field is located off the coast of Denmark, the facilities at the Tyra field are key infrastructure as more than 90 of the country’s natural gas are processed and send to shore via the Tyra facilities New processing and accommodation platforms will replace the existing platforms at the two centres The new facilities
will be situated 225 km west of Esbjerg The proposed developments at the Tyra East complex include an 18 188 t gas processing topside for the Tyra East G platform, two wellhead topsides for Tyra East B 1 763 t) and C 1 366 t), and a 2 480 t riser topside at Tyra East E 

Scope Of Work

AGM in assisting ABL Norway acted as Marine Warranty Survey for the following activities.

  1. Attend and approve final weighing of TEG Deck 19 410 MT
  2. Attend and approve skidded load out of TEG Deck from fabrication location to the quay side and from the quay side onto “GPO EMERALD”
  3. Attend and approve sailaway of TEG Deck loaded on “GPO EMERALD
RECENT PORTFOLIO

Checkout similar work